The timeline below highlights the key stages of the Chapel's history
Completed Chapel is reopen to visitors again
Dedication of the completed Chapel
Completion of the main structure
Work commences on site
The first delivery of stone for the completion of the Lancing College Chapel porch arrives on site.
Masonry work begins off site
Contract signed with Chichester Stoneworks
Launch of the public campaign
Neil Holland's impression of Michael Drury's design to complete the west wall, to be built by 2021
Michael Drury's design for a three-arched porch
Michael Drury commissioned to produce new scheme
Blind tracery in west arches
Sir Robert Woodard lays a foundation stone
North porch dedicated in memory of Basil Handford
Organ reinstated on west gallery
West wall and rose window dedicated
Artist's impression of Dykes Bower's solution, seen from the north-west.
Stephen Dykes Bower's design for the west end
The Friends of Lancing Chapel founded
Tapestries designed by Amy Chilston and woven on the William Morris looms for the apse
Sir George Oatley's design for the west end
War Memorial Cloister built and dedicated
Installation of Gilbert Scott stall canopies and other furnishings
Chapel dedicated
West end boarded up
Laying the floor of the Chapel
Chapel nearing completion except for the west end link to the school
Windows, buttresses and roofs being constructed from east to west
RH Carpenter's & W Slater's design for the west end
Crypt taken into use as school chapel
Chapel Foundation Stone laid
S Mary & S Nicolas College founded by The Revd Nathaniel Woodard